| Town of Newington Road Projects Fiscal Year 2008 - 2009
Cedar Street (Rt 175) from Willard Avenue to Mill Street |
D.O.T. Road Improvements |
Lane closures will be limited 9:00 a.m. and 3:00 p.m., Monday-Friday. |
April 2008 |
September 2008 |
Garfield Street from Willard Avenue to Mill Street Ext |
Bridge Repair |
Area closed to traffic. |
6/23/2008 |
8/22/2008 |
Willard Avenue (Rt 173) from Cedar Street to W. Htfd. Town Line |
D.O.T. Mill and Overlay |
Lane closures limited 9:00 a.m. to 3:00 p.m. Monday - Friday |
July 2008 |
August 2008 |
Main Street (Rt 176) from Robbins Avenue to Hartford Avenue |
D.O.T. Mill and Overlay |
Lane closures limited 9:00 a.m. to 3:00 p.m. Monday - Friday. Paving delayed until tomorrow 08/13 and will continue into next week. |
June 2008 |
August 2008 |
Hartford Avenue (Rt 176) from Main Street to Hartford Town Line |
D.O.T. Mill and Overlay |
Lane closures limited 9:00 a.m. to 3:00 p.m. Monday - Friday. Paving delayed until tomorrow 08/13 and will continue into next week. |
July 2008 |
August 2008 |
| Hall Court |
Road Reconstruction |
Project to begin in August |
|
|
Audubon Avenue from Garfield Street to Willson Avenue |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
Browning Street |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
Hillcrest Avenue from Browning Street to Wilson Avenue |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
Bonair Avenue from Main Street to Walsh Avenue |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
Basswood Street |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
Henry Aveue |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
| Marlboro Street |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
| Coachman Lane |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
| Louis Street |
Road Reconstruction |
Project completed |
5/6/2008 |
7/11/2008 |
Dover Road |
Mill and Overlay |
Project completed |
|
|
| Summit Street |
Mill and Overlay |
Project completed |
|
|
| Tom-Lin Road |
Mill and Overlay |
Project completed |
|
|
| Hall Street |
Mill and Overlay |
Project completed |
|
|
| Hartt Lane |
Mill and Overlay |
Project completed |
|
|
| Lowrey Place |
Mill and Overlay |
Project completed |
|
|
| John H Stuart Drive |
Mill and Overlay |
Project completed |
|
|
| Centerwood Road |
Mill and Overlay |
Project completed |
|
|
Timothy Street from Robbins Avenue to Brockett Street |
Mill and Overlay |
Project completed |
|
|
| Ledgecrest Drive |
Mill and Overlay |
Project completed |
|
|
Carriage Hill Drive |
Mill and Overlay |
Project completed |
07/30/08 |
August 2008 |
|
|
|
|
| |