Road Projects

Fiscal Year 2008 - 2009

 Location

 Project Type

 Comments

 Start

Est. Complete

Cedar Street (Rt 175)
       from Willard Avenue
       to Mill Street

D.O.T. Road Improvements Lane closures will be limited 9:00 a.m. and 3:00 p.m., Monday-Friday.

April 2008

September 2008

Garfield Street
       from Willard Avenue
       to Mill Street Ext
Bridge Repair

Area closed to traffic.    

6/23/2008

8/22/2008 

 Willard Avenue (Rt 173)
       from Cedar Street
       to W. Htfd. Town Line

D.O.T. Mill and Overlay Lane closures limited 9:00 a.m. to 3:00 p.m. Monday - Friday

July 2008

August 2008

Main Street (Rt 176)
       from Robbins Avenue
       to Hartford Avenue
D.O.T. Mill and Overlay Lane closures limited 9:00 a.m. to 3:00 p.m. Monday - Friday.  Paving delayed until tomorrow 08/13 and will continue into next week.

June 2008

August 2008

Hartford Avenue (Rt 176)
       from Main Street
       to Hartford Town Line  
D.O.T. Mill and Overlay Lane closures limited  9:00 a.m. to 3:00 p.m. Monday - Friday.  Paving delayed until tomorrow 08/13 and will continue into next week.

July 2008

August 2008

Hall Court Road Reconstruction Project to begin in August
          
Audubon Avenue 
       from Garfield Street
       to Willson Avenue
Mill and Overlay Project completed

07/30/08

August 2008

Browning Street

Mill and Overlay Project completed

07/30/08

August 2008

Hillcrest Avenue
       from Browning Street 
       to Wilson Avenue

Mill and Overlay Project completed

07/30/08

August 2008

 Bonair Avenue
       from Main Street
       to Walsh Avenue

Mill and Overlay Project completed

07/30/08

August 2008

Basswood Street

Mill and Overlay Project completed

07/30/08

August 2008

Henry Aveue

Mill and Overlay Project completed

07/30/08

August 2008

Marlboro Street Mill and Overlay Project completed

07/30/08

August 2008

Coachman Lane Mill and Overlay Project completed

07/30/08

August 2008

Louis Street Road Reconstruction Project completed  5/6/2008  

7/11/2008

Dover Road

Mill and Overlay Project completed
Summit Street Mill and Overlay Project completed
Tom-Lin Road Mill and Overlay Project completed
Hall Street Mill and Overlay Project completed
Hartt Lane Mill and Overlay Project completed
Lowrey Place Mill and Overlay Project completed
John H Stuart Drive Mill and Overlay Project completed
Centerwood Road Mill and Overlay Project completed

Timothy Street
       from Robbins Avenue
       to Brockett Street

Mill and Overlay Project completed
Ledgecrest Drive Mill and Overlay Project completed

Carriage Hill Drive

Mill and Overlay Project completed

07/30/08

August 2008